Wednesday, 15 January 2020

Cables In and Cables Out

Tuesday 14th Jan


Not a day to be working outside but we need to get some jobs under our belts. A good turnout with 9 of us (plus Mike S and Paul D on comms work).

So first of all its off to Toddington in the diesel railcar to lay all the cables required for the new southern point machines, ground signal and trackside phone.

Some shallow trenches need digging in the ballast to route the cables from the yellow tubes under the track to their appropriate connection points.




And then the removal of the concrete lids from the cable troughs


And then the threading of the cables through the yellow plastic tubes under the track. All the cables are routed from the troughing which runs down the Cotswold side of the track



Cables then fed into the troughs


All the cables have been previously cut to length leaving a generous allowance at each end for connection - none were too short!!

Then all cables are  buried and  the troughing lids are replaced again--no sign of anyone having been here!


So, an explanation of the cables of which there are seven
 Two go to the ground signal for its lamp and its detector. One goes to the phone situated next to the ground signal and two go to the  adjacent point machine - one cable serves the motor for normal and reverse position and one serves detection for normal and reverse positions.
The final two cables serve the other point machine.

This picture shows the layout looking towards Toddington signal box


Having fed the cables through the troughing they will terminate at the adjacent lineside cabinets from where  cables ready feed back to the signal box.
All connections here still to be made but now far too wet and windy for further work - lunch beckons!

I may have regaled you with these shots before but just in case here are the two point machines now fitted with all their detection bars and stretchers




So, that's all of "cables in" - now for "cables out". The job we didn't finish last week was the removal of three remaining lengths of redundant 30 pair cable along the southern stretch from Greet tunnel. We used the railcar to assist using Malcolm W's new fixture to clamp this rather unwieldy cable to the trailer


And then dragged it out to deposit it back in Winchcombe yard. This shot taken  out of a rather wet railcar window (warped the track a bit!) Three trips via the tunnel 



 Carriage and Wagon have agreed to weld the baseplate to the CRC bracket post for us on Wednesday, so the final act today was to manoeuvre it into their workshop. Tele handler to the rescue


And position it on a pair of pedestals - important that the baseplate is in the correct orientation relative to the two holes at the top which locate the clamping blocks - Malcolm W will be on hand to advise. 


Curly

3 comments:

  1. A great and informative blog. Thank you.

    ReplyDelete
  2. Thanks for the Blog. Nice to see the Railcar out and about.

    ReplyDelete

  3. My dad was diagnosed with Parkinson’s disease.his symptoms were shuffling of feet,slurred speech,degradation of hand writing, horrible driving skills, right arm held at 46 degree angle, things were tough for me, but now he finally free from the disease with the help of total cure from ULTIMATE LIFE CLINIC, he now walks properly and all symptoms has reversed, he was having trouble with balance especially at night, getting into the shower and exiting it is difficult,getting into bed is also another thing he finds impossible.we had to find a better solution for his condition which really helped him a lot,the biggest helped we had was ultimate life clinic they walked us through the proper steps,i recommended this www.ultimatelifeclinic.com to anyone who also needs help.

    ReplyDelete