Plenty of feverish activity going on to prepare for the commissioning of Broadway signal box!
Yesterday and today we have reached the point of no return where the ground frame at the south end of the station and the hand lever for the headshunt have now been disconnected from the pointwork.
Headshunt first where the stretcher connection has been changed over - just a small length of rodding fitted to complete it
A bit of adjustment on the turnbuckle and a call to the box to check operation
Points and facing point lock working OK but reported as requiring a very stiff pull. All this rodding and the various pilots haven't been used since installation 8 years ago so we need to give it some serious exercise!
A bit of wrestling to get the 4 bolts holding the yellow hand lever base from the extended sleeper ends but we don't give up without a fight - large stillsons with scaffolding pole extension needed!
Sam has already checked the gauge and fpl settings on the siding points
Back at the south end removal of the ground frame proceeds
Only the four concrete supports remain - these will stay for now
Points, detector rods and fpl now all connected.
Work is continuing with our electrical team to finalise and test the acceptance lever system between Toddington and Broadway.
Curly
It has been a long time coming! At last that beautiful box will get some use!