Thursday 28th June
Only three of us at Broadway today. I had to miss our normal Tuesday, although there was a small gang here who did stuff other than stools!
So here is a brief summary from Tuesday.
The connection of signal 7 (platform 1 starter wooden post) to the box has now been tidied up so that the wire is supported at 20ft intervals - 7 rollers have been attached to the platform wall to support the wire :
There is a tricky area at the end of the platform ramp where the wire has to divert over the top of the rods to "squeeze" through. We should have left the two slabs out that we removed to get the rodding through! It works well with no obvious rubbing points.
Neil C has marshalled a pile of cable troughs on the edge of platform 2 - these will be collected by the diesel railcar for moving to Winchcombe for installing a new cable from the siding renewal work up towards the signal box. The existing cable is buried under the track and will probably get damaged. So better safe than sorry!
So back to today and the dear old rodding. We dug in a further three stools and concreted them in plus the other 5 that were prepared the previous week.
With the four runs of rodding now installed over all the concreted stools it looks the business:
There are now 7 more stools to put in before we reach the point where two of the compensators will go. We hope to get Steve and his mini digger in to prepare the hole for a substantial concrete block. Once we have laid out the positions we can determine how much to cut off the end of a sleeper to get it all in.
Finished off with a shot of Dinmore Manor appearing out of the shadows
Note in this picture that we have upgraded to an electric mixer after all the problems we had with the petrol one!
Curly
Saturday, 30 June 2018
Wednesday, 20 June 2018
Advancing North
Tuesday 19th June 2018
Following the interest shown in Block Bells and the expectancy of sonorous tones expected from Broadway signal box in due course, I can announce that we are going to install a "Church Bell" - and here it is:
I am reliably informed that the six types of block bell normally used are:
Church, Ordinary Round, Flat Round, Cow, Sheep, Gong.
I'm sure Church will sound best!
Back to stool planting. Firstly we unloaded another 20 lengths of rodding from our diminishing store at Winchcombe. These are now residing in the 6ft waiting to be put in once the concrete has set on the next batch of stools:
John P and Carl S started by dismantling the shuttering from last week's run of concreting and filling in the ballast round them:
George busied himself assembling some more stool/roller assemblies on the makeshift cabinet bench while Foremarke Hall rolled by
Still quite a few more needed to get us to the end of the platform - but sufficient to keep us going today:
A total of 28 stools have now been installed which takes us almost up to the footbridge. Probably another half dozen to get us to the point where the first pair of compensators need to be for the first set of points and fpl:
Just 5 of these left for concreting next week.
Couldn't resist climbing up the bracket signal to get an overhead view of Foremarke Hall on its last Broadway run round of the day:
Curly
Following the interest shown in Block Bells and the expectancy of sonorous tones expected from Broadway signal box in due course, I can announce that we are going to install a "Church Bell" - and here it is:
I am reliably informed that the six types of block bell normally used are:
Church, Ordinary Round, Flat Round, Cow, Sheep, Gong.
I'm sure Church will sound best!
Back to stool planting. Firstly we unloaded another 20 lengths of rodding from our diminishing store at Winchcombe. These are now residing in the 6ft waiting to be put in once the concrete has set on the next batch of stools:
John P and Carl S started by dismantling the shuttering from last week's run of concreting and filling in the ballast round them:
George busied himself assembling some more stool/roller assemblies on the makeshift cabinet bench while Foremarke Hall rolled by
Still quite a few more needed to get us to the end of the platform - but sufficient to keep us going today:
A total of 28 stools have now been installed which takes us almost up to the footbridge. Probably another half dozen to get us to the point where the first pair of compensators need to be for the first set of points and fpl:
Just 5 of these left for concreting next week.
Couldn't resist climbing up the bracket signal to get an overhead view of Foremarke Hall on its last Broadway run round of the day:
Curly
Tuesday, 12 June 2018
Connected and Disconnected
Monday, 11th June
Firstly, apologies to my observant blog readers. I got carried away with the detector connections last week to the Wooden post starter signal - this was of course wrong and should have featured the new bracket signal (yet to be installed approx a panel length south of the points). Will explain this in more detail when we put the detector in.
So, to today. Four of us at Broadway. No trains running so we are going to temporarily disconnect the ground frame rods at the south points and connect up to the rodding runs from the signal box. We availed ourselves of the P Way trolley to save a bit of carrying to and fro:
With the ground frame disconnected we could now line out the positions for the point and fpl cranks on the steel plates that were installed last week. Firstly four pilot holes by Malcolm:
Followed by John P on the magnetic drill:
Note that the orange connecting link (here connecting to the point stretcher) has an insulated joint to keep the integrity of the track circuit) :
We had the generator with us today so that we could use the angle grinder for cutting the several short lengths required for connection. And of course two more holes needed in each end - achieved using the "high energy input" hole punch.
And here we are all connected up. George was sent off to the signal box to pull the levers and after a bit of adjustment all works well:
We left ourselves a bit tight for time at the end of the day but managed to get the ground frame re-connected ready for Tuesday's services.
So.. .. when the time comes it will be a relatively simple task to changeover to signal box operation. Just a bit of tidying up and tamping required round the concrete blocks.
Curly
Firstly, apologies to my observant blog readers. I got carried away with the detector connections last week to the Wooden post starter signal - this was of course wrong and should have featured the new bracket signal (yet to be installed approx a panel length south of the points). Will explain this in more detail when we put the detector in.
So, to today. Four of us at Broadway. No trains running so we are going to temporarily disconnect the ground frame rods at the south points and connect up to the rodding runs from the signal box. We availed ourselves of the P Way trolley to save a bit of carrying to and fro:
With the ground frame disconnected we could now line out the positions for the point and fpl cranks on the steel plates that were installed last week. Firstly four pilot holes by Malcolm:
Followed by John P on the magnetic drill:
Note that the orange connecting link (here connecting to the point stretcher) has an insulated joint to keep the integrity of the track circuit) :
We had the generator with us today so that we could use the angle grinder for cutting the several short lengths required for connection. And of course two more holes needed in each end - achieved using the "high energy input" hole punch.
And here we are all connected up. George was sent off to the signal box to pull the levers and after a bit of adjustment all works well:
We left ourselves a bit tight for time at the end of the day but managed to get the ground frame re-connected ready for Tuesday's services.
So.. .. when the time comes it will be a relatively simple task to changeover to signal box operation. Just a bit of tidying up and tamping required round the concrete blocks.
Curly
Wednesday, 6 June 2018
A Change of Direction
Tuesday 5th June
We have decided to pause our efforts going South with the rodding - we can't do anything meaningful with with the setting of the cranks on the blocks that we installed last week until the connections from the ground frame are temporarily disconnected. So the grand plan is to do this next Monday (a non-running day) . We will then re-connect the ground frame (having checked that everything works from the box) leaving everything ready for connection to the signal box at a later date.
In answer to one of the questions to the blog last week regarding the positioning of the rollers that the rodding moves on. After several pulls on the levers it appears that rollers (having random positions in their slots initially) all adopt the same position along the run - so a pure rolling action of the roller stub axles in their slots is achieved (ie much reduced friction).
However, the Eagle eyed observer will note that some rollers do not adopt this regimented position - this is because some of the lengths of rodding are not perfectly flat which means that some rollers do not make contact and do not move!
Similarly, some of the rodding lengths are not perfectly straight laterally which may result in contract with the sides of the rollers - so a certain amount of friction is unavoidable.
Anyway, enough of this roller talk and back to today's activity.
We are now marching northwards with the installation of stools. These have now morphed into the four wheel variety :
Quite a lot of time spent bolting the rollers onto the bases. Each set has 10 bolts. The bolts we happen to be using are a bit longer than they need to be so the winding up of nyloc nuts is a bit labour intensive- but very secure.
Here's Peter B our American volunteer from Hawaii (the current volcanic activity is not on his island) - over here for the summer, having a good workout with the spanners :
Our logistics for concreting today left a bit to be desired. We manhandled many barrow loads of aggregate from the back of the pickup by the station to a pile at the end of platform 2. A barrow crossing needs a Barrowcrossing:
Concrete then mixed with a very temperamental petrol mixer
which somewhat hampered our progress today:
Then barrowed up the platform and shovelled into a bucket to be handed down to Jim P below
We have decided to pause our efforts going South with the rodding - we can't do anything meaningful with with the setting of the cranks on the blocks that we installed last week until the connections from the ground frame are temporarily disconnected. So the grand plan is to do this next Monday (a non-running day) . We will then re-connect the ground frame (having checked that everything works from the box) leaving everything ready for connection to the signal box at a later date.
In answer to one of the questions to the blog last week regarding the positioning of the rollers that the rodding moves on. After several pulls on the levers it appears that rollers (having random positions in their slots initially) all adopt the same position along the run - so a pure rolling action of the roller stub axles in their slots is achieved (ie much reduced friction).
However, the Eagle eyed observer will note that some rollers do not adopt this regimented position - this is because some of the lengths of rodding are not perfectly flat which means that some rollers do not make contact and do not move!
Similarly, some of the rodding lengths are not perfectly straight laterally which may result in contract with the sides of the rollers - so a certain amount of friction is unavoidable.
Anyway, enough of this roller talk and back to today's activity.
We are now marching northwards with the installation of stools. These have now morphed into the four wheel variety :
Quite a lot of time spent bolting the rollers onto the bases. Each set has 10 bolts. The bolts we happen to be using are a bit longer than they need to be so the winding up of nyloc nuts is a bit labour intensive- but very secure.
Here's Peter B our American volunteer from Hawaii (the current volcanic activity is not on his island) - over here for the summer, having a good workout with the spanners :
Our logistics for concreting today left a bit to be desired. We manhandled many barrow loads of aggregate from the back of the pickup by the station to a pile at the end of platform 2. A barrow crossing needs a Barrowcrossing:
Concrete then mixed with a very temperamental petrol mixer
which somewhat hampered our progress today:
Then barrowed up the platform and shovelled into a bucket to be handed down to Jim P below
We managed to complete six stools today with a further three ready for concrete - so a modest start.
We were treated to KEII twice today with well populated carriages:
Curly
Subscribe to:
Posts (Atom)