Wednesday, 23 July 2025

Relaxing a few more stiff pivots

 Tuesday 22nd July

Off to Broadway again today to continue with the checking of the operation of the point rodding.

Last week we had to remove the seized adjustable crank for the headshunt fpl - again this was solid and will need some heat - so a spare one (well oiled!) is being fitted


A bit of digging out under the steel plate to get a spanner on the bolt heads


And then it's back in position



Report from the signal box that the lever pulls nice and smoothly.  

Meanwhile opposite us on the headshunt 3850 waits for the hand operated points to be changed for the run round down platform 2


Now if you follow the connection from the adjustable crank across the tracks to the 4ft of the headshunt you can see the connection to the facing point lock - all this is now working smoothly, but will not be operational until the hand operated connection is eventually removed.


So this concludes the northern end pointwork - its now off to the Evesham Road  Bridge end to check out all the pivoting units. In each case we are disconnecting the point rodding to make sure the cranks move. No seizures here but some are pretty stiff and need vigorous twisting with penetrating oil to get free movement. 


The temp compensators were  tight and needed the central link removing to free up all the joints


In the end we were satisfied that everything was in order and all runs pulled OK from the signal box.

Next time we will check the operation of the signals.

Stand back to let 2807 past.


Curly

Saturday, 19 July 2025

Another Stiff Povot

 Tuesday 15th July

Another visit to Broadway today to continue with the checking of the operation of the pointwork. The seized compensator that we removed last weeik has now been replaced with a spare one. We were unable to free up the seized one using brute force - it will need some heat.

Manhandling it off platform 2


And bolting it into position - works fine now.


Meanwhile at the other compensator position we had to reduce the length of one of the rodding runs which needed the re-drilling of the bolt holes for the connectors:


We then progressed up to the North sidings where the rodding is directed at right angles via a crank under the tracks to the headshunt points where this rodding run will eventually be connected. These points are currently operated by hand lever.
So, communicating with Peter W in the signal box by phone, when the point lever was tried, it would not move. It became obvious that there was another seizure!
And here is the culprit hiding in the undergrowth




This adjustable angle crank would not pivot so it had to be removed.
This turned out to be another one needing heat!

Back at the workshop at Winchcombe we continue to recondition signal parts from the Gotherington distant signals





Note that we are getting very much more organised with racking to store parts - 


We are very happy with our new working conditions! 
There is still a lot of "stuff" in the old carriage workshop/messroom that needs sorting out or throwing away though.

Curly

Wednesday, 2 July 2025

Having seizures at Broadway



 Tuesday 1st July

Our second visit to  Broadway today to sort out a few problems with the point rodding and it's associated connections. Last week we visited the signal box to check the operation of the point levers to make sure that they were functional.

This revealed some problems. A seized pivot on the exit from the tunnel under platform 2 and a seized compensator halfway up platform 2. 

So the team leaping into action today ready with the ladder to descend to track level once the first engine has run round:



Here's the replacement crank ready to go. We haven't managed to unseize the seized one yet. Although this had been oiled when installed, all the years that it hadn't been moved and being open to the elements contributed to its seizure!


Very awkward getting it to fit in between all the other cranks - John P having to crawl into the tunnel and attempt to get the nuts and spanner on underneath the steel plate:





There are four temperature  compensators in the rodding runs to the siding points and headshunt points at the north end, they are set on steel plates in pairs:


One of these is seized solid and won't move so needs disconnecting and taken back to the workshop for dismantling.

Also there is a problem with the rodding length here, so once we have re-fitted the compensator we will solve this




Got it in the barrow for wheeling back up the platform.

Back at the workshop we failed to free the seized arm - will need a good soak with release oil before we try again next week


Hwever we have a spare one so will that will be fitted instead.

Work also continues with the restoration of the parts now dismantled from the Gotherington up distant signal - here's its finial is having the old paint removed


We're never short of signal parts to clean and paint!

Curly