Thursday, 24 August 2017

Heritage Threads

Tuesday 22nd Aug

Another jaunt to Broadway for us today. A bit more unfinished business at the wooden signal post at platform 1 south and continuation of the mammoth task of mechanical locking.

But first a view of the wooden post in all its glory with the scaffolding removed. The only remaining task up top is the fitting of the lamp case - we can do this off the ladder when we bring the right bolts for the job!


And just to prove that it works here's Peter B lifting the balance weight




Meanwhile down below we have to fit an angle bracket to bring a signal wire out towards the track. This produced a fair number of expletives because the attachment of this had to be made to the steel boot. Four 1/2" BSW tapped holes required in true heritage fashion. First of all we broke a drill with just enough of a flute sticking out to eventually remove it with an adjustable wrench - phew!.
A bit of an awkward position with the ladder in the way but John P succeeded valiantly:




Then Keith L achieved his tapping badge after we managed to find some tapping grease among the kit in the signal box- what a difference a bit of grease makes .





And then the angle bracket in position - just a splash of black gloss required to smarten it up:




Meanwhile back in the locking room Malcolm was busy doing some trial fitting of an electric  lock to determine where the bolting has to go to ensure correct alignment with the vertical tappet blades. There are sixteen of these to fit to the bottom rail and will be connected to the tappet blades with couplings which are currently being made in the machine shop at Toddington.



And finally , we now have the rodding stools back from zinc plating - all looking rather fine and weather resistant - as soon as track and ballast are in through the station we can make a start at laying them out


 Curly

Wednesday, 9 August 2017

Set in Concrete

Tuesday 8th August

Five of us off from Winchcombe to Broadway today with the main objective of setting a vertical pulley wheel on a new concrete block at the base of signal 39 (end of platform 2 north) - hope I'm not going to get my norths and souths mixed up this week!
This pulley will re-direct the signal wire from the balance weight arm of the ground  (shunt) signal through 90 Deg towards the track. First a bit of pick-axing and digging to remove some stubborn ash sapling roots (of which there are many on this embankment) - must say the task has been made much easier following a major embankment clearing job by the Broadway group last week.



and then with a bit of on the spot shuttering in place the "pouring" of the concrete followed. It took 5 large barrow loads to fill it. Jim P is on the shovel here



The pulley is mounted on a fabricated bracket which is pressed into the concrete, it sits on a small wooden frame to prevent it sinking any further than the desired height.






The alignment and clearances were then checked using a length of rope. 



Them back to the signal box for a few more tasks. The cabinet I mentioned in last week's blog has now got some substantial shelves fitted. Jim P, Richard C and Peter B exercised their carpentry skills in sawing, drilling and screwing. We now have an enviable storage facility!

I







Meanwhile I walked off south to the wooden post to finish off its waterproofing with a liberal coating of black sealant round the top of the steel boot 




An update on the locking system under the box. John P and Malcolm have fittted the missing locking tray so we now have a full set. 



 Malcolm is now pushing on with the lengthy process of fitting locking bars, cutting slots, drilling and tapping to attach the brass locks, etc, etc. I will attempt to explain an example of what is going on here.  A-channel locking (the row at the very top of the trays) means that when lever no.2 is pulled (route indicator signal) this locks all levers of opposing signals coming in from Toddington, and locks the FPL and point levers - we tried this out and it works - quite a jigsaw - glad Malcolm is on the case!
Here is a close-up  of the Lock for lever 2 on A-channel


You will note that there are some redundant slots on these tappet blades from a previous "life" - some new slots will require cutting in  different positions. 

While I'm in the explaining mood here is the extent of the signalling installation that we will be putting in at Broadway for the current layout. You should all be familiar  with the north end by now, but the  additional signalling up there will be a double  ground signal  at the route indicator  and one in the 6ft.  north of the points. 

Going south, the platform 2 starter will be the LH arm of the existing bracket signal (the RH arm will be taken off).  

 Platform 1starter is the wooden post.

Then there will be a new bracket signal approx 100yards south of Evesham Road Bridge with 2arms and 2call-on arms for the approach from Toddington.

Then an Advanced Starter Signal just north of Childswickham bridge.

An Outer Home Signal 720 yards south of the box 

A Working Distant Signal (motor operated) a further 600 yards south 

So in summary, we  have one bracket, 3 posts and 3 ground signals still to instal. Plenty to be going at. 

Curly


Wednesday, 2 August 2017

A Bit More Finishing off

Tuesday 1st August

Just a very short blog today. Several more things to do to the signals at Broadway. Signal 39 (platform 1 north) needed a bit of fettling. Malcolm did a trial fitting of the disc to the ground signal to ensure that the red stripe was exactly horizontal - luckily OK ( sorry no picture as I was up on top of the wooden signal at the north end). The disc won't be left on until the signal is fully operational.
Then out with the paint brushes to touch up bits of scuffing, bolts, etc. And finally removal of the scaffolding - any further work up top can be accessed via the signal's ladder. Here's the finished job (well almost)


Bit more touching up of the paintwork on no.38 opposite and here are the pair waiting to control the headshunt and siding


There will be some further work required here at no.39 to instal vertical pulley wheels to orientate the signal wires to the correct alignment - another concrete block to cast!

Meanwhile back at the south end we are giving the wooden post another coat of white gloss - this is the fifth coat of paint it has had now so should be well protected. Keith L makes a start at the top - having got up there we saw that the safety hoop needed a top coat of black gloss - what shall we do first , black or white?!



Hope to get a picture of the finished signal next week with scaffolding removed.

Finally, Carl S has acquired a large metal cabinet which we have manhandled into the locking room. This will be used for the storage of tooling. It is extremely useful to have a kit of basic tools at each signal box.


Curly

Monday, 31 July 2017

At long Last!

A big push last Tuesday to see if we could find the elusive cable fault effecting the pair for the Box to Box circuit between Winchcombe and Gotherington. We speak as if it is just one fault but since it doesn't test the same from each end, it is probably several different ones.

With Mike holding the Fort with his trusty 1960's SA9083 tester at the cable head in Winchcombe, Kevern and Paul set off to firstly check out  a possible just before the Tunnel.  They then moved on the Far Stanley and found some crimps that could be improved.  There is no truth in the rumour that Paul met Dr Livingstone whilst exploring the undergrowth!.  Mike then moved to the other end at Gotherington. A quick test and, why should we be surprised, it worked!!

So after two years of reports of gradual stages, we now have a full set of similar Concentrators throughout the system. And a fully operational Box to Box system as well (not that our Strowger kit ever lets us down!)
Hopefully this standardisation  will make life easier for the Signalmen as well as being more attractive within the Signal Boxes themselves

Heres a few pics of the finished installations, sorry there's no pic of Cheltenham. I'm sure there's one somewhere

As the waitress says " Enjoy"
Toddington




Winchcombe
Gotherington           

Wednesday, 26 July 2017

The Four Nearly Finished

Tuesday 25th July

Six of us at Broadway today to progress the fittings on 3 signals and to deliver the final piece of the locking tray that we have now acquired. Locking activity is for another day


To be fitted here



The Route Indicator signal was our first destination to remove the shuttering round the concrete slab that has been constructed to mount a ground signal. We were impressed with the track that has now been laid and clipped as far as this signal - things are moving  a-pace, points next



 


This signal is now essentially complete except for its lamp casings and the frosted glass diffuser.
Quite a bit of paint chipping has occurred during its transfer from Winchcombe and assembly so I spent a while touching up the , mainly black, paintwork.

 


Then over to signal 39. Quite a lot to do here. Firstly to cast a concrete block to secure the base of the ladder.  Jim P is puddling the concrete that has been mixed by Keith L in a wheelbarrow




Then the mounting of the ground signal on its elevated mount - this will provide good visibility for the drivers. The disc is going to be approx 5 ft above ground level (perhaps not a good idea to call this a ground signal!)
Before fitting :


And a couple of shots after assembly . Note that the front disc still has to be fitted, we will leave this off until a future date. Also you  may have noticed that we did not realise, because we were using the bracket to mount the ground signal,  the length of the black portion on the post was insufficient - this has been rectified and everything is now black up to the upper clamp! With hindsight, the length of the larger diameter of the post could have been a little longer to give us a bit more leeway for juggling all these fittings - but it all functions and looks good:




Then off we went to our pride and joy - the wooden post - now firmly secured in its concrete boot. The ladder has been fixed at the top with its rather unusual configuration :


  And at the bottom with a some concrete


We had time at the end of the day to put some undercoat on areas of the paintwork  that had been damaged during its rise from obscurity  and it will get a final coat of white gloss next time. 

Round the route indicator signal and number 39, nature is rapidly encroaching so John P felt in an attacking mood and had a go at clearing some of the growth 


The track in the foreground will probably be sitting on sleepers by the time you read this!!

Curly



Wednesday, 19 July 2017

Getting There

Tuesday 18th July

Just three of us off to Broadway today to progress the fitting of some of the remaining parts to the Signals Numbers 38 and 39 at the north ends of the platforms were first. The penultimate part to fit to number 38 (platform 1 side) was the angle crank which is clamped to the post at the bottom. The down rod which connects the balance weight arm to the spectacle plate at the top still has to be completed (we have the length measurement for it - fine adjustment will be taken up by a screwed adjuster on its lower end)



Then over to number 39 ( these numbers refer to the number of the lever in the signal box - number one starting nearest the door). Now this signal is another kettle of fish and we needed several attempts to fit everything on at the bottom end. Apart from the balance weight arm and the angle crank there is a large bracket on which a ground signal will be mounted:



Once clamped into its preferred position we had a fouling problem with the angle crank - a small corner of the bracket will have to be removed by angle grinder next time - otherwise it all just fits. We measured the length required for this signal's down rod which we will configure back at base.







Meanwhile up above Malcolm is drilling a hole to fix the detector



After lunch we headed southwards to the wooden post south of platform 1 to fit its spectacle plate, ladder, finial and down rod.  The down rod fitted beautifully and was adjusted to show a nice horizontal arm. Here's John P viewed from above making the final tweak



And a view from a distance




A bit more work needed to finish this signal off yet. A trial fitting of the lamp case behind the spectacle plate reveals that we need to make a spacer to bring the lamp lens to align with the centre of the coloured spectacles.

And finally a view of number 38 with the scaffolding removed - bit of a weird angle but I assure you the arm is horizontal!





Curly

Friday, 14 July 2017

Lets Concentrate now!

Friday 7th July

Kevern and Paul  met up to reinstall the concentrator at Gotherington. Mike S went to Winchcombe We knew that the line to Winchcombe was still not usable so we had planned to "borrow" another pair just top prove it worked but  it still didn't, we hadn't foreseen that we had a broken wire inside the unit at Winchcombe!
Problem is that with each concentrator we have had to commission them in stages and as each new stage comes on stream new faults can appear, including a faulty Krone strip at Toddington!.
By definition this is all done between signal boxes that are a few miles apart, it all takes time. So to eliminate the dodgy cable pr, we took the new Goth Unit to Winchcombe and it still didnt work over a few metres of cable. Eventually Kevern found the problem, a broken wire  inside the Winchcombe unit so we are now confident that when the new cable is connected ( to get rid of a number old joints inside and around the Tunnel area, we should be "cooking on Gas" as they say.
In the meantime of course its the block bells backed up by the trusty dial- up Strowger PAX that will keep the signalmen in contact.

Monday 10th July

Kevern went off to  Racecourse early this morning, I attended a bit later at Goth and was able to prove that the section between Racecourse and Gotherington now works Box to Box. When Goth is switched out then we hope that the system will work  over twice the distance ie Racecourse to Winchcombe. Kevern has just one more choice relays with a lower operating current to try in that case, buts just be positive.

Perhaps I can elaborate further on the Box to Box design side. The original scheme for the SPT's was all Loop Calling, AC ringing  (ROLI like POTS). But when you need to call between boxes we had a problem since the Calling Box couldn't send a loop and anything else would have needed bi- directional transmission bridges. The answer was to make the bridge so that it would respond not only to a loop from its own SPT's but also to 50v dc from  the other box and we had to inhibit the AC ringing so that the sensitive electronic relays in the bridges were not destroyed by an inadvertent burst of 80vac.
Again it took time and was the reason why the system has been installed stage by stage but we do now seem to be getting there

No new pics this time, I'm sure you have seen enough of us peering at things!!

Mike S