Wednesday, 18 December 2024

Merry Christmas

 Just a quick update to let you know we're still here.  As mentioned previously I was away in Australia for all of October and a number of our crew were away undergoing their own maintenance.  Since November we have been gradually moving parts and equipment from the old coach to our new home in our freshly finished workshop.  There's been quite a lot to do, along with a handful of minor repairs and adjustments out on the line.  The weather hasn't helped, see the photo below showing the new workshop in late November, but we are making progress.  Hopefully we'll have a few photos of the inside of the new building soon, once we've got it looking something like.  Also we should be starting some winter maintenance in early January; some disconnection and reconnection and set up of one of our older sets of mechanical points at Winchcombe (P-Way changing timbers) and probably a strip and refit of a signal post at Gotherington.

Until then have a Merry Christmas and a Happy New Year.

Neil and the S&T gang.



Friday, 6 September 2024

Upgrading Signage

 Tuesday 3rd Sept

A short trip to CRC today to replace some very tired warning signs. The first ones are at the crossing by the signal box:

John B and John P removing the very faded one:


And the bright new one (complying with current regulations) in place:


This one has much more of a visual impact

Then it's back to base at Winchcombe to do a bit of tidying up at the far end of the new workshop. It is planned to reposition the container which is presently opposite the C & W workshop at the side of the set of blue containers here. This to provide more secure and dry storage for our signal spares.


The whole of this area will be tidied up with a covering of stone/spent ballast

Note the drains here which we have surrounded with aprons of concrete.


This area will be used to tidy up the various  larger signalling items which currently are spread around Winchcombe yard.


That's all from me for a while - having a full knee replacement next week so no more clambering over ballast for some time!

Curly

 

Thursday, 5 September 2024

And Finally at Gotherington

 Last Thursday George and I went to Gotherington for one last time, with the remaining parts for the ground signal and a tin of black paint.  We fitted the lamp case, balance weight and arm and the disc face and back blind and re-connected it.  We then touched up a few damaged and missed areas of paint on the new signal and ground signal and painted a few bolt heads.  Finally went to the box to correctly set up the signal wire for the new signal (the wire was just a bit too slack).  The adjuster on the lever tail was near the end of its travel and was also partly seized, so we removed the adjuster, placed it in the vice, freed it up and set it toward the longer end of its adjustment.  We then cut the signal wire outside of the box and re-jointed it using a short piece of wire and reducing its effective length by around 6" (we had to use an additional piece of wire and make two joints, as jointing a wire needs about 6-8" spare wire on each end to 'wrap' the joint, therefore to just cut and re-join a wire makes it around 12-16" shorter, which would have been too short).  Once we'd done this we set the adjuster correctly for a good off on the signal.  That completes the job replacing the old wooden post and refurbishing the disc, cabinet and associated connections around them.  The below photo shows the completed job, with the signal box in the background.


I'm off to Australia for most of October and some members of the gang will be absent for several weeks due to medical procedures.  Therefore there will be little to report for a while.  The good news is that our S&T Workshop is now almost complete, so November should see us moving in and setting up for winter maintenance.

Thursday, 29 August 2024

More at Gotherington

 Tues 27th August 

A bit more work required at Gotherington today. The reconditioned ground signal which has now been cleaned and painted is ready for replacement on its new foundation block.

It's too heavy to transport fully assembled so today just the base casting is being bolted down. The fittings will be put on next week


The cables routed down the Cotswold side of the track here are in need of proper burial and the track circuit feed cables are being re-routed. So a bit more ballast digging required:




A lot tidier now for the cables between the signal and the lineside cabinet adjacent to the line crossing at the end of the platform. The cabinet has also had a coat of silver paint:


Neil C seen here drilling some new holes in the rails with the motorised drill for the repositioned track circuit connections 


Curly

Wednesday, 14 August 2024

Gotherington Signal Finished

 Yesterday a slightly depleted gang of Neil C, Peter B, John P and John B went to Gotherington with a truck loaded with signal parts.  We started at the top of Signal G3's new post, fitting the pivot casting and plunger casting, Neil and Peter on the scaffolding, John P fixing parts to the rope as required and John B keeping lookout and passing over parts when needed.  We then fitted the spec plate, lamp casing, lamp back blind, signal arm, and then hung the down rod from the spec plate, finally fitting the finial before moving to the bottom of the post.  At the bottom we offered up the balance weight casting and arm to the down rod and clamped that to the post, then fitted the signal wire angle crank and short connecting wire.  Finally we fitted a down rod guide half way up the down rod.  The operating part of the signal was now complete.  There then followed a quick partial dismantling of the scaffold and wait for the next train to pass, before we offered the ladder up through the scaffold.  The ladder turned out to be exactly the right length, so the ladder bracket and hoop were fitted just below the top fittings and the ladder foot buried in the ground.  We finally dismantled and cleared away the scaffold.  

Unfortunately the wooden post had a wheel and sling at the base rather than the angle crank now fitted and we didn't have enough signal wire with us, nor the correct thimble and shackle, to replace the sling and fully reconnect the signal to the box, therefore we temporarily fixed the signal off (Gotherington Box currently being switched out).  The signal wire and lamp cable will be fitted by Neil C in the near future, to bring the signal fully back into service.



Peter B takes a selfie as Neil C leans on the signal spec plate.



John B, John P and Neil C by the completed signal.

Monday, 5 August 2024

Gotherington Signal Update

 

Last Monday we enlisted the help of our colleagues in P-Way who came out with the Road Rail Vehicle and lifted a replacement post into the prepared hole in the concrete where the wooden post once lived.  We wedged the post near upright with timbers placed alongside it in the hole.


The RRV then picked up the rotten wooden post and headed back to Winchcombe.

On the Tuesday the gang went to Gotherington, and erected the scaffold around the new post.


Here we see the gang pausing whilst 7903 Foremarke Hall comes past, John B doing his lookout duties on the left of shot.

Once the train had passed we completed the erection of the scaffold and stood the post properly upright in the centre of the hole, tying it off at the top of the scaffold.  We then mixed and poured round the post a cement heavy and quite wet concrete mix, trowelling it up to the post to prevent water pooling against the post base.  Once that was completed we went back to Winchcombe to continue preparing fittings for the post.


The next visit will see us fitting out the post and possibly bringing it back into service.  once the scaffold is removed we will also fit the recently restored disc signal.


Thursday, 25 July 2024

Gothering Signals

 Tuesday 23rd July

There have been several trips to Gotherington in recent weeks to replace the wooden signal post and to recondition the adjacent ground signal.

The wooden post has proved to be completely rotten. Having carefully removed the fittings using the scaffolding tower, nothing more than a gentle push sent it toppling down!  Here is the result:



Now the challenge to remove the remainder of the rotten wood from the concrete block. A replacement metal post will be concreted in here. Peter B  is tickling out the stubborn pieces of not quite so rotten pieces:


And John P up to his armpit to clear out the hole - 2ft deep about as far as we could get - should be sufficient to concrete in the metal replacement . 


On completion of the clearance of the hole a team photo as Dinmore Manor pulls out of Gotherington in the  background.


The ground signal and its also rotten mounting woodwork had already been removed and a new section of sleeper fitted to the two "submerged" concrete blocks . 


The signal has been dismantled back at Winchcombe and is in the process of being cleaned and painted.

Curly